Data centre planning applications in Northumberland (County)
Northumberland (County) has 7 data-centre planning applications tracked since 2025 (7 awaiting decision, 0 permitted); 3 received in the last 30 days. Data as of 2026-08-17.
Received in the last 30 days
| Application | Description | Stage | MW | Status | Received |
|---|---|---|---|---|---|
| 26/02818/FUL Land East Of Sleekburn Business Centre West Sleekburn Northumberland | Application for 11/33kV temporary substations and associated development for the construction and early operation of the proposed Cambois Data Centre Campus | Other | Undecided | 2026-08-10 | |
| 26/02817/FUL Land At Former Power Station Site On Northern Side Of Cambois Cambois Northumberland | Application for 20kV temporary substations for construction and early operation of proposed Cambois Data Centre Campus (Application Reference: 24/04112/OUTES) | Other | Undecided | 2026-08-10 | |
| 26/02810/SCREEN Land At Factory Road Cambois Northumberland | Screening opinion for a proposed data centre development - Reference: LSE_00837_EIA Screening | EIA screening | Undecided | 2026-08-07 |
4 older applications in Northumberland (County) — full history back to 2025, status-change events, and facts extracted from the planning documents (MW, floorspace, applicant, cooling, grid connection — each with a verbatim quote and the source PDF) are on the Pro plan. See plans.
JSON: /v1/applications?area=…